Can I define an activity to use resources for a portion of that activity?

activity

Yes, an activity definition can specify that a resource is used for any number of intervals within the activity as long as the earliest usage is not before the start of the activity or past the end of the activity. That is, the duration of the activity must span all of the resource usage intervals. Example: a surgical procedure may require an operating room for the entire duration, one surgeon starting 30 minutes after the procedure starts, another for the last 30 minutes of the procedure etc. The quantities of a required resource can also vary during an activity’s duration.